Under construction

Krishna Curve

by KRISHNA MINERALS

CTS G8, G12A, AND G12B, F.P. NOS. 27A AND 27B, Mumbai, 400054

High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 63.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Official RERA facts

Registration
P51800030635
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
63.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drains60%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposal95%
Water conservation /Rain water harvesting60%
Fire protection and fire safety requirements60%
Electrical meter room, sub-station, receiving station65%

Building & registration

RERA registered
Sept 2021
Floors
17

Buyer community

Connect with other buyers and owners of Krishna Curve โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Krishna Curve. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.