Under construction

Lodha Kandivali Project - Tower 2

by Lodha Developers Limited

174C1, Akurli Village, 400101

Jul 2026
Possession
81.8%
Built
1
Complaints
149
Units
Caution
  • Promised amenities not started. Clubhouse is at 0% build with possession due Jul 2026 per the RERA filing.

Official RERA facts

Registration
P51800031351
Status
New
Stage
Certificate Signed
Possession
July 2026originally December 2025
Construction
81.8% complete
Units sold
147 of 149

RERA complaint record1 record

  • ComplaintCC1260037220 Jan 2026
    Himanshu Shekhar vs Lodha Developers Limited

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths30%
Water Supply30%
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drains50%
Landscaping & Tree Planting40%
Street Lighting30%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water30%
Solid Waste Management And Disposal30%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements60%
Electrical meter room, sub-station, receiving station30%
Aggregate area of recreational Open Space20%

Building & registration

RERA registered
Oct 2021
Floors
39
Unit mix
149 res ยท 0 comm
Architect
Pradeep M Kamble

Buyer community

Connect with other buyers and owners of Lodha Kandivali Project - Tower 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Lodha Kandivali Project - Tower 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.