Under construction
Lodha Kandivali Project - Tower 2
174C1, Akurli Village, 400101
Jul 2026
Possession
81.8%
Built
1
Complaints
149
Units
Caution
- Promised amenities not started. Clubhouse is at 0% build with possession due Jul 2026 per the RERA filing.
Official RERA facts
- Registration
- P51800031351
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2026originally December 2025
- Construction
- 81.8% complete
- Units sold
- 147 of 149
RERA complaint record1 record
- ComplaintCC1260037220 Jan 2026Himanshu Shekhar vs Lodha Developers Limited
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths30%
Water Supply30%
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drains50%
Landscaping & Tree Planting40%
Street Lighting30%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water30%
Solid Waste Management And Disposal30%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements60%
Electrical meter room, sub-station, receiving station30%
Aggregate area of recreational Open Space20%
Building & registration
- RERA registered
- Oct 2021
- Floors
- 39
- Unit mix
- 149 res ยท 0 comm
- Architect
- Pradeep M Kamble
Buyer community
Connect with other buyers and owners of Lodha Kandivali Project - Tower 2 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Lodha Kandivali Project - Tower 2. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.