Lodha Kandivali Project - Tower 4

by Lodha Developers Limited

174C1, AKURLI VILLAGE, 400101

May 2025
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (May 2025) has passed with construction at 81.8%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due May 2025 per the RERA filing.

Official RERA facts

Registration
P51800031532
Status
New
Stage
Certificate Signed
Possession
May 2025
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths30%
Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Space15%
Closing Parking45%

Building & registration

RERA registered
Oct 2021
Floors
23

Buyer community

Connect with other buyers and owners of Lodha Kandivali Project - Tower 4 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Lodha Kandivali Project - Tower 4. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.