Under construction

ALAG ASHTAPAD

by CONTOUR DEVELOPERS LLP

5661 PT, Kurla, 400075

Caution
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 90.9%.
Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800031922
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
90.9% complete
Units sold
85 of 107

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Street Lightingnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Nov 2021
Floors
17
Unit mix
107 res ยท 0 comm
Architect
ARCHO CONSULTANTS

Buyer community

Connect with other buyers and owners of ALAG ASHTAPAD โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ALAG ASHTAPAD. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.