Under construction

ALAG OLIVE

by ALAG OLIVE LLP

184C, GHATKOPAR EAST, 400075

Dec 2024
Possession
89.5%
Built
0
Complaints
108
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 89.5%.
Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800032510
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
89.5% complete
Units sold
74 of 108

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains70%
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Jan 2022
Floors
17
Unit mix
108 res ยท 0 comm
Architect
ARCHO CONSULTANTS

Buyer community

Connect with other buyers and owners of ALAG OLIVE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ALAG OLIVE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.