All RERA projects
🏗️
Under construction

Runwal Bliss - Wing F

by Evie Real Estate Private Limited

1004P,1005P,1007P,1007/3,1007/4,1009P,1009/5-6,1010P,1013P,1014P,1014/1-6,1017/1-6,1018,1018/1-9, Kurla, 400042

Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2026, now proposed Jul 2029 per the RERA filing.

Official RERA facts

Registration
P51800032824
Status
New
Stage
Certificate Signed
Possession
July 2029originally December 2026
Construction
46.1% complete
Units sold
87 of 228

RERA complaint record

Complaint data not yet synced for this project.

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.