KRISHNA KUNJ PHASE 1

by PRINCE HOUSING AND HOSPITALITY PRIVATE LIMITED

461, 463, 463/1 TO 4, 464, 464/1 TO 6, Borivali, 400062

High risk
  • Possession delayed ~2 yrs. Originally promised Jan 2025, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 46.4%.

Official RERA facts

Registration
P51800033187
Status
New
Stage
Certificate Signed
Possession
March 2027originally January 2025
Construction
46.4% complete
Units sold
32 of 137

RERA complaint record

Complaint data not yet synced for this project.