Center Plaza Phase 1

by B V ENTERPRISES

FP No 25 and FP No 26, Borivali, 400097

High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51800034832
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2023
Construction
81.8% complete
Units sold
27 of 28

RERA complaint record

Complaint data not yet synced for this project.