Borivali New Roma Sadan CHSL

by SUMUKH INFRAPROJECT

659.20, Borivali, 400092

High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2023, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 36.4%.

Official RERA facts

Registration
P51800045284
Status
New
Stage
Certificate Signed
Possession
March 2027originally June 2023
Construction
36.4% complete
Units sold
6 of 23

RERA complaint record

Complaint data not yet synced for this project.