PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SHRADDHA PEARL

by SHRADDHA LANDMARK PRIVATE LIMITED

356 PT, VILLAGE HARIYALI, 400083

Dec 2025
Possession
76.2%
Built
0
Complaints
83
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 76.2%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2025 per the RERA filing.

Official RERA facts

Registration
P51800046124
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
76.2% complete
Units sold
63 of 83

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2022
Floors
69
Unit mix
83 res ยท 0 comm
Architect
Archo Consultants

Buyer community

Connect with other buyers and owners of SHRADDHA PEARL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHRADDHA PEARL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.