ASMI BUSINESS CENTRE

by ASMI CORPORATION

SURVEY NO.3 PART HISSA NO.6 OLD CTS NO.51 PART AND NEW CTS NO 51A/B, Borivali, 400063

High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2025, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P51800046269
Status
New
Stage
Certificate Signed
Possession
December 2028originally December 2025
Construction
29.9% complete
Units sold
83 of 164

RERA complaint record

Complaint data not yet synced for this project.