352 (PT), Village Hariyali, 400083

Dec 2025
Possession
81.8%
Built
0
Complaints
153
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 81.8%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2025 per the RERA filing.

Official RERA facts

Registration
P51800046277
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
81.8% complete
Units sold
115 of 153

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Community Buildingsnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2022
Floors
48
Unit mix
153 res ยท 0 comm
Architect
Archo Consultants

Buyer community

Connect with other buyers and owners of Shraddha Panache โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Shraddha Panache. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.