Under construction

MAHESH BHAVAN C. H. S. L.

by LMP GROUP MAHESH BHAVAN

125,125/1 to 125/3, GOREGAON EAST, 400063

Apr 2025
Possession
100%
Built
0
Complaints
0
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2025 per the RERA filing.

Official RERA facts

Registration
P51800046529
Status
New
Stage
Certificate Signed
Possession
April 2025
Construction
100% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains90%
Landscaping & Tree Plantingnot started
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Water95%
Solid Waste Management And Disposal95%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station90%

Building & registration

RERA registered
Aug 2022
Floors
12

Buyer community

Connect with other buyers and owners of MAHESH BHAVAN C. H. S. L. โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MAHESH BHAVAN C. H. S. L.. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.