Lodha Vikhroli-Signet

by Lodha Developers Limited

CTS no. 67 Part,67A,67/1 to 67/5,67/9 to 67/18, Kurla, 400079

Caution
  • Possession delayed ~2 yrs. Originally promised Jun 2027, now proposed Jun 2029 per the RERA filing.

Official RERA facts

Registration
P51800047504
Status
New
Stage
Certificate Signed
Possession
June 2029originally June 2027
Construction
48.9% complete
Units sold
634 of 907

RERA complaint record

Complaint data not yet synced for this project.