PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

DJ AMORE2

by DHIRAJ narayandas JADHWANI

359,360, MUMBAI, 400074

Mar 2026
Possession
58.5%
Built
0
Complaints
22
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2026) has passed with construction at 58.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2026 per the RERA filing.

Official RERA facts

Registration
P51800048275
Status
New
Stage
Certificate Signed
Possession
March 2026originally April 2025
Construction
58.5% complete
Units sold
6 of 22

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Dec 2022
Floors
9
Unit mix
22 res ยท 0 comm

Buyer community

Connect with other buyers and owners of DJ AMORE2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DJ AMORE2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.