Under construction

Komal Kounteya CHSL

by Rander Bandhu Corporation LLP

370, Borivali, 400091

Caution
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 94.5%.
Kandivali / BorivaliMid-income

Self-sufficient Gujarati-dominated family belt beside the National Park.

Growth drivers:
Metro 2A/7, station upgrades, big-brand township launches.
Who buys here:
Families seeking space and community at sane prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800049376
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
94.5% complete
Units sold
13 of 71

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains50%
Landscaping & Tree Planting40%
Solid Waste Management And Disposal75%
Water conservation /Rain water harvesting60%
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station75%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2023
Floors
22
Unit mix
71 res ยท 0 comm
Architect
Manoj Jangid

Buyer community

Connect with other buyers and owners of Komal Kounteya CHSL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Komal Kounteya CHSL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.