ATRIA ARSHABHARAT

by DHARTI AAKAR REALTY

157, Mumbai, 400104

Caution
  • Behind schedule. Possession is due Aug 2026 but construction is only at 36.8%.

Official RERA facts

Registration
P51800050652
Status
New
Stage
Certificate Signed
Possession
August 2026
Construction
36.8% complete
Units sold
0 of 0