Caution
  • Possession delayed ~2 yrs. Originally promised Jun 2025, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51800052504
Status
New
Stage
Certificate Signed
Possession
December 2026originally June 2025
Construction
80.5% complete
Units sold
9 of 28