All RERA projects
๐๏ธ
Under construction
MPR NILESH
by MPR NILESH
973/A, Borivali, 400068
Caution
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2027 per the RERA filing.
Official RERA facts
- Registration
- P51800056192
- Status
- New
- Stage
- Certificate Signed
- Possession
- January 2027
- Construction
- 71.4% complete
- Units sold
- 13 of 58
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 19 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposal95%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- May 2024
- Floors
- 16
- Unit mix
- 47 res ยท 11 comm
- Architect
- SHRIKANT VICHARE & ASSOCIATES
Buyer community
Connect with other buyers and owners of MPR NILESH โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MPR NILESH. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.