High risk
- Possession delayed ~3 yrs. Originally promised Dec 2017, now proposed Oct 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P51900000050
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2020originally December 2017
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 20 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths70%
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains90%
Landscaping & Tree Planting70%
Street Lighting80%
Water conservation /Rain water harvesting85%
Fire protection and fire safety requirements85%
Electrical meter room, sub-station, receiving station85%
Building & registration
- RERA registered
- Jun 2017
- Floors
- 9
Buyer community
Connect with other buyers and owners of Pratiksha Nagar Phase IV โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Pratiksha Nagar Phase IV. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.