All RERA projects
🏗️
Under construction

La Mer Residences

by EXCELLENT REALTOR DEVELOPERS

CS 227, Ward E, 400008

High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2022, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51900004434
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2022
Construction
66.8% complete
Units sold
69 of 242

RERA complaint record

Complaint data not yet synced for this project.

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.