All RERA projects
🏗️
Under construction

LAKADAWALA HEIGHTS

by AARIAASH DEVELOPERS

1456, Mumbai City, 400008

High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2021, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 7.9%.

Official RERA facts

Registration
P51900005993
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2021
Construction
7.9% complete
Units sold
0 of 0

RERA complaint record

Complaint data not yet synced for this project.