Under construction

Tanishq Wisteria

by Aakaar Tanishq Nirmaan J. V.

846, Ward FSouth, 400015

High risk
  • Possession delayed ~3 yrs. Originally promised Aug 2019, now proposed Sept 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 76.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2022 per the RERA filing.
Parel / Dadar EastPremium

Mill-land towers around Maharashtra's busiest rail junction.

Growth drivers:
Hospital cluster jobs, central location, mill plot launches.
Who buys here:
South-Bombay workers wanting new construction.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51900006567
Status
Ongoing
Stage
Certificate Signed
Possession
September 2022originally August 2019
Construction
76.8% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station70%

Building & registration

RERA registered
Aug 2017
Floors
15

Buyer community

Connect with other buyers and owners of Tanishq Wisteria โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Tanishq Wisteria. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.