All RERA projects
🏗️
Under construction

CONTINENTAL HEIGHTS

by SARAH HOUSING DEVELOPMENT PVT LTD

641,642, Ward E, 400010

High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2024, now proposed Dec 2029 per the RERA filing.

Official RERA facts

Registration
P51900007187
Status
Ongoing
Stage
Certificate Signed
Possession
December 2029originally December 2024
Construction
84.4% complete
Units sold
0 of 0

RERA complaint record

Complaint data not yet synced for this project.

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.