F.W.TOWERMahaRERA P51900009073

by crystal construction corporation

335, 400017

Aug 2026
Possession
21.8%
Built
0
Complaints
1
Units
High risk
  • Behind schedule. Possession is due Aug 2026 but construction is only at 21.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2026 per the RERA filing.

Official RERA facts

Registration
P51900009073
Status
Ongoing
Stage
Certificate Signed
Possession
August 2026
Construction
21.8% complete
Units sold
0 of 1

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
26

Buyer community

Connect with other buyers and owners of F.W.TOWER โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching F.W.TOWER. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.