Under construction

Raheja Imperia - I

by Raheja Universal (Pvt.) Ltd.

434 part of Lower Parel Division, Ward GSouth, 400013

High risk
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 99.5%.
Lower Parel / WorliUltra-luxury

Mill-land skyscraper district โ€” corporate HQs, five-stars and sea-view towers.

Growth drivers:
Coastal Road and Sea Link access, premium office stock, Worli sea-face cachet.
Who buys here:
CXOs, HNIs and investors chasing trophy addresses.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51900009379
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022
Construction
99.5% complete
Units sold
0 of 0

RERA complaint record7 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Spacenot started
Club House and Swimming Pool90%
Extended Podium Level 190%
Extended Podium Level 290%
P0 Level90%

Building & registration

RERA registered
Aug 2017
Floors
61

Buyer community

Connect with other buyers and owners of Raheja Imperia - I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Raheja Imperia - I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.