Neumec Aura

by Aura Monde LLP

C S NO 810/10, Mumbai City, 400031

High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2024, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51900012309
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally June 2024
Construction
39.5% complete
Units sold
3 of 34

RERA complaint record

Complaint data not yet synced for this project.