All RERA projects
🏗️
Under construction

Om Gopal - Floor 3 to 9

by Omkar Realtors and Developers Private Limited

FP No. 569 pt of TPS 4 Mahim Division, Ward GNorth, 400028

High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2020, now proposed Jun 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 90.9%.

Official RERA facts

Registration
P51900012360
Status
Ongoing
Stage
Certificate Signed
Possession
June 2026originally December 2020
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record

Complaint data not yet synced for this project.

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.