Lodha Adrina

by LODHA DEVELOPERS LIMITED

464, Ward GSouth, 400013

High risk
  • Possession delayed ~2 yrs. Originally promised Jul 2024, now proposed Jun 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 88.6%.

Official RERA facts

Registration
P51900014937
Status
New
Stage
Certificate Signed
Possession
June 2026originally July 2024
Construction
88.6% complete
Units sold
229 of 401

RERA complaint record

Complaint data not yet synced for this project.