High risk
  • Possession delayed ~8 yrs. Originally promised Dec 2019, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51900017724
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2019
Construction
100% complete
Units sold
0 of 0

RERA complaint record

Complaint data not yet synced for this project.