All RERA projects
🏗️
Under construction

COMPOSITE BUILDING NO2

by NEUMEC AND SANGAM JV

345/PT366/PT370/PT245/PT335/PT374/PT, Mumbai City, 400021

High risk
  • Possession delayed ~5 yrs. Originally promised Jun 2022, now proposed Jun 2027 per the RERA filing.

Official RERA facts

Registration
P51900018301
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2022
Construction
100% complete
Units sold
0 of 0

RERA complaint record

Complaint data not yet synced for this project.