All RERA projects
🏗️
Under construction

BALAJI ARCADE

by SHREE DEVELOPERS

625 PT,627 PT,628 AND 629 PT, Ward FNorth, 400031

High risk
  • Possession delayed ~3 yrs. Originally promised Sept 2023, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51900020641
Status
New
Stage
Certificate Signed
Possession
December 2026originally September 2023
Construction
84.1% complete
Units sold
7 of 19

RERA complaint record

Complaint data not yet synced for this project.

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.