"The Mansion" By ABIL

by Arindam Developers LLP

1519, Mumbai City, 400007

High risk
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 87.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2025 per the RERA filing.
Girgaon / Grant RoadPremium

Heritage chawl-and-wadi belt in cluster redevelopment mode.

Growth drivers:
Cluster redevelopment policy, Metro 3, Coastal Road.
Who buys here:
South-Bombay natives staying local in new towers.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51900022063
Status
New
Stage
Certificate Signed
Possession
March 2025originally March 2024
Construction
87.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drains75%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvesting75%
Fire protection and fire safety requirements85%
Electrical meter room, sub-station, receiving station95%

Building & registration

RERA registered
Aug 2019
Floors
41

Buyer community

Connect with other buyers and owners of "The Mansion" By ABIL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching "The Mansion" By ABIL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.