Under construction

SAI ARADHYA

by MANGALMURTI DEVELOPERS

F.P. NO. 188 AND 195 TPS-IV, DADAR WEST, 400028

Mar 2027
Possession
75.2%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2024, now proposed Mar 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51900023477
Status
New
Stage
Certificate Signed
Possession
March 2027originally March 2024
Construction
75.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Dec 2019
Floors
23

Buyer community

Connect with other buyers and owners of SAI ARADHYA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI ARADHYA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.