Under construction

Supreme Melange

by Supreme Ventures LLP

514 A/10, Ward FNorth, 400014

High risk
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 86.6%.
  • Promised amenities not started. Gymnasium, Landscaped Garden are at 0% build with possession due Jun 2024 per the RERA filing.

Official RERA facts

Registration
P51900026166
Status
New
Stage
Certificate Signed
Possession
June 2024
Construction
86.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)65%
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Gymnasium on Podiumnot started

Building & registration

RERA registered
Aug 2020
Floors
22

Buyer community

Connect with other buyers and owners of Supreme Melange โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Supreme Melange. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.