Under construction

THE EDGE

by TEJUKAYA CORP PRIVATE LIMITED

3/52, 3A/52, 3A1/52 AND 3B/52, Ward FSouth, 400012

Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2028, now proposed Dec 2030 per the RERA filing.

Official RERA facts

Registration
P51900032613
Status
New
Stage
Certificate Signed
Possession
December 2030originally December 2028
Construction
8.2% complete
Units sold
169 of 379

RERA complaint record

Complaint data not yet synced for this project.