Under construction

VIVA

by LIVSTONE BUILDERS LLP

7/1865, Ward E, 400011

Caution
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Jun 2027 per the RERA filing.

Official RERA facts

Registration
P51900047459
Status
New
Stage
Certificate Signed
Possession
June 2027originally December 2025
Construction
56.5% complete
Units sold
30 of 93

RERA complaint record

Complaint data not yet synced for this project.

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.