PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

AARADHYA AVAAN

by SHREEPATI SKIES (R R CHATURVEDI)

309, Mumbai City, 400007

Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51900048675
Status
New
Stage
Certificate Signed
Possession
December 2030
Construction
56.7% complete
Units sold
163 of 545

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 19 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drains95%
Landscaping & Tree Planting15%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposal30%
Water conservation /Rain water harvestingnot started
Energy managemcnt20%
Fire protection and fire safety requirements30%
Electrical meter room, sub-station, receiving station70%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jan 2023
Floors
75
Unit mix
545 res ยท 0 comm
Architect
B N SHAH & ASSOCIATES

Buyer community

Connect with other buyers and owners of AARADHYA AVAAN โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AARADHYA AVAAN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.