Under construction

Indira

by Sugee Developers Pvt. Ltd.

1770, Shivaji Park, Dadar, 400028

Apr 2026
Possession
50.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Apr 2026) has passed with construction at 50.9%.

Official RERA facts

Registration
P51900048976
Status
New
Stage
Certificate Signed
Possession
April 2026
Construction
50.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements20%
Electrical meter room, sub-station, receiving station40%

Building & registration

RERA registered
Jan 2023
Floors
20

Buyer community

Connect with other buyers and owners of Indira โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Indira. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.