Under construction

Waterview

by Waterview

310 and 311, Mumbai City, 400006

Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51900055626
Status
New
Stage
Certificate Signed
Possession
June 2028
Construction
57.5% complete
Units sold
1 of 11

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 19 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths5%
Water Supply5%
Sewerage (Chamber, Lines, Septic Tank , STP)5%
Storm Water Drains5%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting5%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Apr 2024
Floors
34
Unit mix
11 res ยท 0 comm
Architect
Pradeepmkamble and associates

Buyer community

Connect with other buyers and owners of Waterview โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Waterview. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.