Under construction

Indiabulls Park 3

by Lucina Land Development Limited

71/6A ,69/1A, 69/1B , 71/5A ,81/7 , 81/8 , 81/9 , 64/1 , 64/2 , 71/11 , 71/13 , Panvel, 410207

High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Apr 2028 per the RERA filing.
  • 29 RERA complaints. 29 complaint records are disclosed against this project on MahaRERA.

Official RERA facts

Registration
P52000000488
Status
Ongoing
Stage
Certificate Signed
Possession
April 2028originally December 2024
Construction
43.9% complete
Units sold
768 of 937

RERA complaint record29 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jul 2017
Floors
44
Unit mix
937 res ยท 0 comm
Architect
Rakhi Ubhare

Buyer community

Connect with other buyers and owners of Indiabulls Park 3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Indiabulls Park 3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.