๐๏ธ
Under construction
RAMCHANDRA RESIDENCY PHASE 1
SURVEY NO 21 HISSA NO 3C, Bhuwaneshwar (CT), 402109
Sept 2020
Possession
100%
Built
1
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2020 per the RERA filing.
Official RERA facts
- Registration
- P52000001918
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2020originally March 2019
- Construction
- 100% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC1260377218 Jun 2026UTPAL SOMCHAND RANA vs CRK INFRASTRUCTURE
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Jul 2017
- Floors
- 6
Buyer community
Connect with other buyers and owners of RAMCHANDRA RESIDENCY PHASE 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching RAMCHANDRA RESIDENCY PHASE 1. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.