All RERA projects
๐๏ธ
Dec 2020
Possession
99.5%
Built
1
Complaints
0
Units
Caution
- Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 99.5%.
Official RERA facts
- Registration
- P52000002967
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2020originally December 2019
- Construction
- 99.5% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC00600000019902727 Nov 2021Sonika Goyal vs Sunny Buildtech Pvt. LtdOrder of Sonika Goyal (1).pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirements95%
Electrical meter room, sub-station, receiving station90%
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 13
Buyer community
Connect with other buyers and owners of ORCHID BLISS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching ORCHID BLISS. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.