Under construction

Anand SagarMahaRERA P52000003192

by Akbar Mohamadali Kazi

174, ULWE, 410206

Sept 2023
Possession
71.8%
Built
0
Complaints
40
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2020, now proposed Sept 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2023) has passed with construction at 71.8%.

Official RERA facts

Registration
P52000003192
Status
Ongoing
Stage
Certificate Signed
Possession
September 2023originally December 2020
Construction
71.8% complete
Units sold
7 of 40

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains50%
Street Lighting50%
Water conservation /Rain water harvesting25%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station25%
Aggregate area of recreational Open Space50%
Open Parking10%

Building & registration

RERA registered
Aug 2017
Floors
15
Unit mix
34 res ยท 6 comm
Architect
Disha Architect

Buyer community

Connect with other buyers and owners of Anand Sagar โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Anand Sagar. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.