Under construction

TULSA NAMDEO RESIDENCY

by RAM VASDEV BATHIJA

17/67, Ulawe, 410206

Jun 2019
Possession
56.8%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2019) has passed with construction at 56.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2019 per the RERA filing.

Official RERA facts

Registration
P52000005472
Status
Ongoing
Stage
Certificate Signed
Possession
June 2019
Construction
56.8% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of TULSA NAMDEO RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching TULSA NAMDEO RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.