SWAGAT VILLAGE
S.R.NO. - 63/4, 64/2, 64/3, 64/4, 65/2B., Karjat, 410101
Jun 2027
Possession
79.5%
Built
1
Complaints
0
Units
High risk
- Possession delayed ~4 yrs. Originally promised Jun 2023, now proposed Jun 2027 per the RERA filing.
Official RERA facts
- Registration
- P52000005559
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2027originally June 2023
- Construction
- 79.5% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC00600000042946226 Mar 2024Arvind Vinayakrao Arvind vs Ankit PatelOrder of Arvind.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths60%
Water Supply40%
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Storm Water Drainsnot started
Landscaping & Tree Planting85%
Street Lightingnot started
Community Buildings30%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements30%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 9
Buyer community
Connect with other buyers and owners of SWAGAT VILLAGE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SWAGAT VILLAGE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.