Anand Nagar Phase 1
by Anubhavshri Realty Pvt. Ltd.
Survey no. 51/1 to 51/76, A, Lonere, 402104
Jun 2022
Possession
99.1%
Built
15
Complaints
0
Units
High risk
- Recovery warrant issued. MahaRERA has issued 1 recovery warrant against this project โ the strongest enforcement action on record.
- Possession delayed ~4 yrs. Originally promised Jun 2018, now proposed Jun 2022 per the RERA filing.
- 15 RERA complaints. 15 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 99.1%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Jun 2022 per the RERA filing.
Official RERA facts
- Registration
- P52000005747
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2022originally June 2018
- Construction
- 99.1% complete
- Units sold
- 0 of 0
RERA complaint record15 records
- ComplaintCC125035556 Oct 2025Krishna Kumar Gupta vs AYG Realty Private Limited
- Misc. applicationCC00600000037493129 Mar 2023Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.
- Misc. applicationCC00600000037493329 Mar 2023Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.
- Misc. applicationCC00600000037493529 Mar 2023Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.
- Recovery warrantCC00600000037492829 Mar 2023Krishna Kumar Gupta vs AYG Realty Private Limited
- Misc. applicationCC00600000037492829 Mar 2023Krishna Kumar Gupta vs AYG Realty Private Limited
- ComplaintCC00600000037493329 Mar 2023Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.Scanned Order CC005_374933.pdf on MahaRERA
- ComplaintCC00600000037493529 Mar 2023Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.Scanned Order CC006_374935.pdf on MahaRERA
- Misc. applicationCC00600000037493029 Mar 2023Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.
- ComplaintCC00600000037492829 Mar 2023Krishna Kumar Gupta vs AYG Realty Private Limited374928 order ds.pdf on MahaRERA
- ComplaintCC00600000037493029 Mar 2023Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.Scanned Order CC006_374930.pdf on MahaRERA
- ComplaintCC00600000037493129 Mar 2023Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.Scanned Order CC006_374931.pdf on MahaRERA
- ComplaintCC0060000001975006 Jul 2021Krishna Kumar Gupta vs AYG Realty Private LimitedOrder of Krishnakumar Gupta vs AYG.pdf on MahaRERA
- Misc. applicationCC00600000016122515 Oct 2019Mr. Olvy Fernandes vs AYG Realty Pvt. Ltd.Order CC006_161225.pdf on MahaRERA
- ComplaintCC00600000016122515 Oct 2019Mr. Olvy Fernandes vs AYG Realty Pvt. Ltd.Order CC006_161225.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths60%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drainsnot started
Landscaping & Tree Planting20%
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 6
Buyer community
Connect with other buyers and owners of Anand Nagar Phase 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Anand Nagar Phase 1. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.