Possession
99.1%
Built
15
Complaints
0
Units
High risk
  • Recovery warrant issued. MahaRERA has issued 1 recovery warrant against this project โ€” the strongest enforcement action on record.
  • Possession delayed ~4 yrs. Originally promised Jun 2018, now proposed Jun 2022 per the RERA filing.
  • 15 RERA complaints. 15 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 99.1%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Jun 2022 per the RERA filing.

Official RERA facts

Registration
P52000005747
Status
Ongoing
Stage
Certificate Signed
Possession
June 2022originally June 2018
Construction
99.1% complete
Units sold
0 of 0

RERA complaint record15 records

  • ComplaintCC125035556 Oct 2025
    Krishna Kumar Gupta vs AYG Realty Private Limited
  • Misc. applicationCC00600000037493129 Mar 2023
    Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.
  • Misc. applicationCC00600000037493329 Mar 2023
    Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.
  • Misc. applicationCC00600000037493529 Mar 2023
    Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.
  • Recovery warrantCC00600000037492829 Mar 2023
    Krishna Kumar Gupta vs AYG Realty Private Limited
  • Misc. applicationCC00600000037492829 Mar 2023
    Krishna Kumar Gupta vs AYG Realty Private Limited
  • ComplaintCC00600000037493329 Mar 2023
    Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.
    Scanned Order CC005_374933.pdf on MahaRERA
  • ComplaintCC00600000037493529 Mar 2023
    Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.
    Scanned Order CC006_374935.pdf on MahaRERA
  • Misc. applicationCC00600000037493029 Mar 2023
    Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.
  • ComplaintCC00600000037492829 Mar 2023
    Krishna Kumar Gupta vs AYG Realty Private Limited
    374928 order ds.pdf on MahaRERA
  • ComplaintCC00600000037493029 Mar 2023
    Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.
    Scanned Order CC006_374930.pdf on MahaRERA
  • ComplaintCC00600000037493129 Mar 2023
    Krishna Kumar Gupta vs AYG Realty Pvt. Ltd.
    Scanned Order CC006_374931.pdf on MahaRERA
  • ComplaintCC0060000001975006 Jul 2021
    Krishna Kumar Gupta vs AYG Realty Private Limited
    Order of Krishnakumar Gupta vs AYG.pdf on MahaRERA
  • Misc. applicationCC00600000016122515 Oct 2019
    Mr. Olvy Fernandes vs AYG Realty Pvt. Ltd.
    Order CC006_161225.pdf on MahaRERA
  • ComplaintCC00600000016122515 Oct 2019
    Mr. Olvy Fernandes vs AYG Realty Pvt. Ltd.
    Order CC006_161225.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths60%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drainsnot started
Landscaping & Tree Planting20%
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of Anand Nagar Phase 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Anand Nagar Phase 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.