TULSI NISARG

by PRISTINE GROUP

107/2/D,108, neral, 410101

Jun 2027
Possession
27.5%
Built
3
Complaints
1
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Jun 2027 per the RERA filing.
  • Behind schedule. Possession is due Jun 2027 but construction is only at 27.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52000005986
Status
Ongoing
Stage
Certificate Signed
Possession
June 2027originally June 2021
Construction
27.5% complete
Units sold
0 of 1

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
9
Unit mix
1 res ยท 0 comm

Buyer community

Connect with other buyers and owners of TULSI NISARG โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching TULSI NISARG. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.