GOURI SHARDA

by SHANKAR SADU MHATRE

PLOT NO 38, Panvel, 400705

High risk
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 32.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2018 per the RERA filing.
Navi Mumbai (Vashi–Nerul)Mid-income

Planned-city order — wide roads, node markets, established social infra.

Growth drivers:
Atal Setu (MTHL), metro lines, the upcoming Navi Mumbai airport.
Who buys here:
Professionals wanting planned-city living with airport-corridor upside.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P52000007381
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
32.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply30%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of GOURI SHARDA — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching GOURI SHARDA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.