SHASHWAT SANKUL

by SAI SMARAN CONSTRUCTION

S NO 26 AND 28 PLOT NO 31 TO 34, Bopele, 410101

Apr 2018
Possession
68.6%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Apr 2018) has passed with construction at 68.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2018 per the RERA filing.

Official RERA facts

Registration
P52000007561
Status
Ongoing
Stage
Certificate Signed
Possession
April 2018
Construction
68.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
ELECTRICAL METER ROOMdone
WATER CONSERVATION RAINWATER HARVESTINGnot started
LANDSCAPING AND TREE PLANTATINGnot started
STORM WATER DRAINnot started
SEWARAGE CHAMBER LINES AND SEPTIC TANKdone
INTERNAL ROADS AND FOOTPATHSnot started
WATER SUPPLYdone

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of SHASHWAT SANKUL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHASHWAT SANKUL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.